Pricing estimates

How to bid landscape installation jobs

Bid landscape installs line by line: site visit checklist, materials takeoff, labor hours, equipment, disposal, contingency and proposal sections.

Ava research teamPublished 7 min read

On this page
  1. What the customer should see in the proposal
  2. Site visit checklist
  3. Build the number from a takeoff
  4. Example: a patio and planting bed, line by line
  5. Labor hours: the line that sinks bids
  6. Sell in winter, build in spring
  7. Options without confusion
  8. Plant guarantees and workmanship terms
  9. Common bid mistakes
  10. Safety and crew planning belong in the bid
  11. After you send it
  12. Frequently asked questions
  13. References

Key takeaways

  • Bid from a takeoff, not a gut number: materials with waste, labor hours by task, equipment days, disposal, subcontractors, contingency, then overhead and profit.
  • Labor hours are the line most often underestimated, and trade wages keep rising: specialty trade contractor hourly earnings were up 4.7% in a year to September 2026[1].
  • Landscapers pay only 19.3% of annual payroll in the first quarter versus 25.9% across all industries[2], so winter is the time to sell spring installs.
  • A proposal customers can say yes to has a clear scope, exclusions, a schedule, a payment schedule and an expiration date.

What the customer should see in the proposal

Homeowners compare landscape bids side by side, and the one that is easiest to understand often wins even when it is not the cheapest. Use the same section order on every proposal so your crew leads, office staff and customers all know where to look.

  1. Project summary in two or three sentences, in the customer’s words where possible.
  2. Site plan or marked-up photo showing beds, hardscape, grade changes and drainage.
  3. Scope by area: what gets removed, installed and restored in each zone.
  4. Plant and material list with sizes, quantities and allowed substitutions.
  5. Exclusions: irrigation changes, permits, utility relocation, rock removal beyond a stated depth, anything not listed.
  6. Schedule: estimated start window, duration and what weather does to it.
  7. Warranty: plant guarantee terms, what voids them (for example, no watering) and hardscape workmanship terms.
  8. Price, payment schedule, expiration date and a signature or e-signature line.

Site visit checklist

A bid is only as good as the visit behind it. Collect these before you leave the property, and photograph each one so the estimator and the crew lead see the same thing.

  • Measurements of every bed, patio, wall and path, with a sketch tied to fixed points such as the house corners.
  • Access: gate widths, slopes and soft ground that decide whether a compact loader fits or work is done by hand.
  • Soil and drainage: standing water, downspouts, compacted fill and existing grade around the foundation.
  • Utilities: plan to call 811 before digging, and note visible meters, irrigation heads and lighting cables.
  • Removal: sod, shrubs, stumps, old pavers and how much will need hauling.
  • Rules: HOA approval, setbacks and any permit triggers for walls or drainage.
  • Customer priorities and budget range, asked directly.

Build the number from a takeoff

  1. Materials with waste

    Quantify plants, soil, mulch, base, pavers, edging and fabric from your measurements. Add a waste factor per material and use current supplier quotes, not last season’s.

  2. Labor hours by task

    Break the job into tasks (demolition, excavation, base, laying, planting, cleanup) and estimate crew hours for each from your own past jobs.

  3. Equipment days

    Charge owned machines at an internal day rate that covers payments, fuel and repairs, and rentals at cost plus handling.

  4. Delivery and disposal

    Price material deliveries, dump fees and hauling trips separately so they never get forgotten.

  5. Subcontractors

    Add quotes for lighting, irrigation or masonry subs with your coordination margin.

  6. Contingency

    Add a stated contingency for unknowns you cannot see, such as buried debris, and say in the proposal what it covers.

  7. Overhead and profit

    Apply your overhead recovery and target profit to the direct cost, then check the result against what similar jobs actually earned.

Example: a patio and planting bed, line by line

Example: a fictional company bids a small backyard paver patio with a new planting bed. The numbers below are illustrative only; use your own costs and markups.

Example bid build-up for a fictional patio and planting bed (illustrative figures)
LineBasisExample amount
MaterialsPavers, base, sand, edging, plants, soil and mulch from supplier quotes, plus waste$4,350
Labor3-person crew, 4 days at 8 hours, loaded rate $32 per hour$3,072
EquipmentCompact loader 2 days and plate compactor, internal day rates$720
Delivery and disposalTwo material deliveries, one dump trailer of sod and soil$480
Contingency5% of direct cost for buried debris or soft subgrade$431
Overhead and profit30% applied to direct cost plus contingency$2,716
TotalBefore tax, valid 30 days$11,769

Example check: the contingency, overhead and profit lines are visible to you, not to the customer. The proposal shows the scope by area and one total, or a total per option.

Labor hours: the line that sinks bids

Materials are easy to price from a supplier quote; labor is where most landscape bids lose money. Base hours on what your crews actually took on similar jobs, and price them at a fully loaded rate. Grounds maintenance workers earned a median $19.27 an hour in May 2025[3], but wages are only part of the cost: benefits made up 30.0% of private employer compensation costs in June 2026[4]. Payroll taxes, workers’ comp and paid downtime sit on top.

Rates keep moving. Average hourly earnings of production and nonsupervisory employees at specialty trade contractors reached $39.05 in September 2026, up 4.7% on a year earlier[1]. If you use masonry, irrigation or lighting subcontractors, expect their quotes to follow that trend, and refresh them for every bid rather than reusing old numbers.

After each job, record actual crew hours per task next to the estimate. Ten jobs of honest data will improve your bids more than any rule of thumb.

Sell in winter, build in spring

Landscaping is lopsided across the year. US landscaping services paid 19.3% of their 2023 annual payroll in the first quarter, against 25.9% across all industries[2]. Winter is quiet in the field but ideal for site visits, design meetings and signed proposals that fill the spring schedule before the rush.

Share of annual payroll paid in the first quarter, 2023Lower first-quarter share means a deeper winter slowdown.
Share of annual payroll paid in the first quarter, 2023Comparison. Landscaping services: 19.3%; All industries: 25.9%.19.3%Landscaping servicesLandscaping services: 19.3%25.9%All industriesAll industries: 25.9%Share of annual payroll paid in the first quarter, 2023Comparison. Landscaping services: 19.3%; All industries: 25.9%.19.3%Landscaping servicesLandscaping services: 19.3%25.9%All industriesAll industries: 25.9%

Source: U.S. Census Bureau, 2023[2]

Show the data
ItemValue
Landscaping services19.3%
All industries25.9%
  • Run a winter design campaign to past customers and recent maintenance clients.
  • Offer a firm start window for proposals signed by a set date.
  • Put an expiration date and a materials clause on every winter bid, because supplier prices may change before you build. See quote expiration dates and deposit rules.

Options without confusion

Two or three options help customers decide, as long as each one is a complete scope rather than a menu of parts. A common structure is a core option (the plan as discussed), an upgraded option (larger plants, a premium paver or added lighting) and a phased option that splits the work across two seasons. Price each option in full and explain the difference in a single sentence.

Example: a fictional proposal offers a core patio and bed, an upgraded version with a seat wall and low-voltage lighting, and a phased version that builds the patio this spring and the planting bed in the fall. The customer who balks at the upgraded total often chooses the phased option instead of walking away.

Plant guarantees and workmanship terms

Warranty language is part of the price, because every replacement plant and callback costs crew time. Decide what you guarantee and for how long, and write the conditions in plain words. Typical conditions include the customer watering as instructed, no damage from pets, vehicles or other contractors, and a cap of one replacement per plant. Hardscape terms usually cover settling and loose units caused by your installation, not frost heave from drainage the customer declined to fix.

Price the guarantee by tracking your own replacement rate. If one plant in twenty fails in the first season on your jobs, build that cost into the plant line rather than absorbing it as a surprise. Offer a longer guarantee as part of the upgraded option, tied to a maintenance agreement, so the plants are cared for by people you trust.

Common bid mistakes

  1. Measuring once. Measure twice and compare; a few square feet per bed adds up across soil, mulch and labor.
  2. Pricing plants at list without availability. Confirm sizes are in stock or name acceptable substitutions in the proposal.
  3. Forgetting access. A gate that will not fit a loader turns a two-day dig into a four-day hand job.
  4. Leaving out restoration. Lawn repair where equipment tracked across the yard is real work and should be a line.
  5. No exclusions list. Anything not written down will be argued about later, usually at the final payment.
  6. Reusing old subcontractor quotes. Ask for a fresh number for every bid.

Safety and crew planning belong in the bid

Hand excavation, loaders and heavy materials carry real risk. Work fatalities among building and grounds cleaning and maintenance workers rose to 356 in 2024 from 337 in 2023[5]. Plan crew size, lifting equipment and traffic control for the job you are bidding, and price them in. A bid that only works if two people carry wall block all day is not a safe or accurate bid.

After you send it

Follow up on a schedule: a call two days after sending to walk through questions, then again before the expiration date. Write down why customers decline, whether price, timing or scope, and review the reasons each quarter. When scope changes after signing, use a written change order; see handling scope changes mid-job.

Frequently asked questions

How much contingency should a landscape bid include?

Use a stated contingency sized to what you cannot see on the site visit, such as buried debris or poor subgrade, and explain in the proposal what it covers. Small, clearly scoped jobs need less than large regrading or demolition work.

Should a landscape proposal show a line-by-line price?

Show scope by area and a total per option. Keep your internal build-up (labor hours, markups, contingency) for your own records; itemized internal costs invite line-by-line haggling.

How long should a landscaping bid be valid?

Pick a window that matches how quickly your supplier prices move, such as 15 or 30 days, and go shorter when they are changing fast. Put the expiration date on the proposal and say what happens to pricing after it.

How do I estimate labor hours for landscape installation?

Break the job into tasks and use actual crew hours from similar past jobs. Track estimated versus actual hours on every job so the next bid is better.

References

  1. U.S. Bureau of Labor Statistics (2026). Current Employment Statistics (not seasonally adjusted), series CEU2023800008 (Specialty trade contractors, average hourly earnings of production and nonsupervisory employees) (opens in a new tab) ↑

  2. U.S. Census Bureau (2023). County Business Patterns 2023: U.S. detail file (cbp23us) (opens in a new tab) ↑

  3. U.S. Bureau of Labor Statistics (2025). Grounds Maintenance Workers: Occupational Outlook Handbook (opens in a new tab) ↑

  4. U.S. Bureau of Labor Statistics (2026). Employer Costs for Employee Compensation — June 2026 (opens in a new tab) ↑

  5. U.S. Bureau of Labor Statistics (2024). Census of Fatal Occupational Injuries Summary, 2024 (opens in a new tab) ↑

Book a demo

See Ava handle your calls.

Book a short demo. We’ll walk through your calls and workflow, and agree what Ava should take care of.

Book a demo