Who pulls the permit, how to track lead times by jurisdiction, keeping homeowners updated and closing every open permit with a passed inspection.

Ava research teamPublished 6 min read

On this page
  1. Permits belong on the schedule
  2. Who pulls the permit
  3. Build a lead-time sheet by jurisdiction
  4. Put permit time into the proposal
  5. Tracking open permits
  6. Getting inspections right the first time
  7. Working well with inspectors
  8. Emergencies and after-the-fact permits
  9. Keeping homeowners informed
  10. Older homes and lead paint
  11. Example: clearing a permit backlog
  12. Measure the process
  13. Frequently asked questions
  14. References

Key takeaways

  • Permits are near universal for residential building: over 99% of privately owned residential buildings are constructed in permit-issuing places[1].
  • The licensed contractor doing the work should normally pull the permit; avoid asking homeowners to pull permits for your work.
  • Keep a lead-time sheet for each jurisdiction you work in and an open-permit tracker sorted by next action, reviewed weekly.
  • Book inspections early, prepare the site with a checklist and close every permit; an open permit can surface years later when the home is sold.

Permits belong on the schedule

For many install and replacement jobs, the permit is the longest lead item. A water heater, furnace, panel upgrade, roof or new circuit can be ready to install in days, and then wait a week or more for approval. Inspections add another dependency at the end. If permit and inspection dates live in someone's inbox rather than on the calendar, crews arrive at jobs that are not ready and finished jobs sit unclosed for months.

The scale of the system is large. As of January 2023 the Census Bureau's Building Permits Survey covered approximately 19,900 permit-issuing places, and over 99% of all privately owned residential buildings constructed are in permit-issuing places[1]. Each place sets its own process, fees and timelines. A company working across several towns and counties is managing several different systems.

Privately owned residential buildings constructed in permit-issuing placesCensus Bureau says over 99 percent
Privately owned residential buildings constructed in permit-issuing placesDonut chart. In permit-issuing places: 99%.In permit-issuing places: 99%99%
  • In permit-issuing places 99%

Source: U.S. Census Bureau, 2026[1]

Show the data
ItemValue
In permit-issuing places99%

Who pulls the permit

Who should pull the permit (confirm local rules)
SituationWho usually pulls itNotes
Your company does the workYour licensed company or qualifierKeeps responsibility and inspections with you
Subcontracted trade workThe licensed subcontractor for their tradeConfirm before scheduling; track their permit too
General contractor jobThe general contractor, plus trade permits as requiredAgree in writing who books each inspection
Homeowner offers to pull itAvoid for your workOwner permits may shift responsibility and can complicate warranty and insurance
Emergency repairYour company, often after the fact where allowedCheck each jurisdiction's emergency rules

Licensing is part of this. Most states require electricians to be licensed[2], and some states and localities require HVAC technicians to be licensed[3]. Permit offices usually check that the applicant holds the right license for the trade and jurisdiction, so keep license numbers, expiry dates and local registrations in one place.

Build a lead-time sheet by jurisdiction

Do not guess permit times. Record them from your own jobs and keep a one-page sheet per jurisdiction that sales and the install coordinator both use.

Example: a jurisdiction lead-time sheet (fictional entries)
FieldExample entry (fictional)
JurisdictionCity of Riverside Falls
Permit types you useMechanical, electrical, roofing
How to applyOnline portal; plans needed for panel upgrades
Typical approval timeMechanical 3 business days; electrical 5; roofing over-the-counter
How inspections are bookedPortal by 3 p.m. for next business day
Inspection windowMorning or afternoon; inspector calls 30 minutes ahead
Common correction itemsDisconnect labelling, condensate termination
Last updatedEach quarter from completed jobs

Update the sheet from your tracker every quarter. When a jurisdiction slows down, sales can set expectations at the proposal stage instead of the office breaking bad news later. Note any seasonal patterns you see in your own records, such as slower approvals in the busiest building months or around holidays, and plan proposals around them.

Put permit time into the proposal

The best moment to manage permit expectations is before the customer signs. Give salespeople the lead-time sheet and ask them to quote a realistic start window that includes the permit step, not the earliest date a crew is free. A proposal that says "installation typically two to three weeks after signing, including city permit approval" sets the clock correctly. A proposal that promises next week and then waits on the city creates an unhappy customer before the first tool comes out of the van.

Include permit fees and the permit step in the proposal itself, so the customer sees them as part of a proper job rather than an extra. If a customer asks to skip the permit to save time or money, explain plainly why you will not: unpermitted work can cause problems with insurance claims, resale and safety, and it puts your license at risk.

Tracking open permits

  1. Open a record at sale

    Create the permit record with the job number, jurisdiction, permit type and target install date.

  2. Apply promptly

    Submit the application within one or two business days of the sale, and log the date and reference number.

  3. Set the next action

    Every open permit has a next action and a date: check status, answer a plan review question, pay a fee, book an inspection.

  4. Link to the install calendar

    Crews are only confirmed when the permit is issued or due before the install date.

  5. Book inspections

    Request the inspection as soon as the work is ready, and record the date and who will meet the inspector.

  6. Close it

    Record the passed inspection and final sign-off, and attach the documents to the job.

Sort the tracker by next action date, not by job. Review it weekly, with special attention to permits issued but not inspected after 30 days, which are the ones most likely to be forgotten.

Getting inspections right the first time

  • Use a pre-inspection checklist for each permit type, built from past correction notices.
  • Make sure the permit card or number is posted or available on site as the jurisdiction requires.
  • Arrange access: confirm the homeowner will be home, or that the inspector can reach the equipment.
  • Have the installer or a lead available by phone during the inspection window.
  • Photograph the finished work before the inspection, including anything that will be covered.
  • If the inspection fails, book the correction and re-inspection immediately, and tell the homeowner what is being fixed.

Working well with inspectors

Inspectors see your work more often than any customer. A good working relationship saves time on every job. Be on time for inspection windows, have the permit and plans ready, keep the site safe and tidy, and answer questions directly. When an inspector writes a correction, fix it properly and ask what they want to see next time; feed the answer into your pre-inspection checklist. Keep notes on each jurisdiction's preferences, such as labelling, documentation or photos they ask for, on the lead-time sheet so every crew benefits.

Emergencies and after-the-fact permits

Some work cannot wait for a permit: a failed water heater in winter, a dangerous electrical fault, a storm-damaged roof that needs to be dried in. Many jurisdictions allow emergency work to start before the permit, with an application filed within a short period afterwards. Know the rule for each place you work, write the emergency permit step into the job workflow and track these permits with the same care as planned ones, since they are the easiest to forget once the emergency is over.

Keeping homeowners informed

Homeowners rarely understand permits, and many assume the contractor is causing the delay. Explain the process at the proposal stage and keep them updated.

  • At sale: "Your installation needs a permit from the city. We apply this week; approval usually takes about five business days, and we will confirm your install date once it is issued."
  • Permit issued: "Good news: your permit is approved. Your install is confirmed for Tuesday and Wednesday with Ray's crew."
  • Inspection booked: "The city inspection is booked for Friday morning. Someone needs to be home to let the inspector in, or tell us how they can reach the equipment."
  • Inspection passed: "Your installation has passed inspection and the permit is closed. Your documents are attached for your records."

Older homes and lead paint

Permits are not the only rule that affects scheduling. EPA's Renovation, Repair and Painting rule requires anyone paid to disturb painted surfaces in homes, childcare facilities and preschools built before 1978 to be certified, with employees trained in lead-safe work practices[4]. Flag the year built at sale; jobs in older homes may need a certified renovator on the crew and extra time for containment and cleanup.

Example: clearing a permit backlog

Example (fictional): an HVAC and electrical company discovered 23 permits that had been issued but never inspected, some more than a year old, after a homeowner's sale was delayed by an open permit. The office manager built a tracker, called each homeowner to book inspections and grouped them by jurisdiction to make the most of inspector visits. Most passed first time; a few needed small corrections. The company now reviews open permits every Monday, and none stays open more than 30 days after the work is finished without a recorded reason.

Measure the process

Track three numbers: days from sale to permit issued by jurisdiction, first-time inspection pass rate by permit type and the count of permits open more than 30 days after work is complete. Use them in the weekly install review alongside the multi-day install calendar and, for roofing work, weather planning.

Frequently asked questions

Who should pull the building permit, the contractor or the homeowner?

Normally the licensed contractor doing the work. Asking homeowners to pull permits for your work can shift responsibility to them and complicate warranty and insurance. Check local rules.

How long do permits take?

It varies widely by jurisdiction and permit type, from same day to several weeks. Record approval times from your own jobs and keep a lead-time sheet for each place you work.

What happens if a permit is never closed?

An open permit can surface during a home sale or insurance claim and may require an inspection years later. Track every permit until it has a passed final inspection.

How can we pass more inspections first time?

Use pre-inspection checklists built from past correction notices, photograph work before covering it and have an installer available during the inspection window.

References

  1. U.S. Census Bureau (2026). Building Permits Survey: Methodology (opens in a new tab) ↑

  2. U.S. Bureau of Labor Statistics (2025). Electricians: Occupational Outlook Handbook (opens in a new tab) ↑

  3. U.S. Bureau of Labor Statistics (2025). Heating, Air Conditioning, and Refrigeration Mechanics and Installers: Occupational Outlook Handbook (opens in a new tab) ↑

  4. U.S. Environmental Protection Agency (2026). Lead Renovation, Repair and Painting Program (opens in a new tab) ↑